PCC Patch 2021 Phase 1 and 2

Project Description:

Each year, the City of Urbandale patches a number of city streets that are in need of repair.  The work is divided into two projects, one in western Urbandale, and one in eastern Urbandale.  Please see below for more details of each phase.

Phase 1 West - Project Status Update - 07/23/2021

The 2021 Patch Project Phase 1 has been awarded to Shekar Engineering.  Shekar has completed the Horizons Ridge neighborhood.  The Contractor is wrapping up work in Telby Knolls west of 156th Street.  

The Contractor will begin working in the Hallbrook Plat 6 neighborhood the week of 7/26.  

The Contractor will have a second crew also starting 7/26 in the Avondale and Glynmor neighborhoods north of Douglas.

Residents will be notified when work will be starting in their neighborhood.  Please see contact info in notices below if you have questions on construction.  Thanks for your patience during this work.

Phase 1

Phase 1 is in western Urbandale and includes the areas from 147th Street to 160th Street and from Maple Drive to Airline Avenue.  

PCC_Key

Phase 2 East - Status Update - 06/29/2021

The 2021 Patch Project Phase 2 has been awarded to Hill Contracting.  Hill Contracting is continuing work on Holcomb Avenue and wrapping up patches on 71st Street.  The Contractor will also begin working on adjacent sidewalk ramps in the next few weeks.

Residents will be notified when work will be nearing their area. Please see contact info in notices below if you have questions on construction.  Thanks for your patience during this work.

Phase 2

Phase 2 is in eastern Urbandale and includes the Holcomb Avenue, the Hickman Frontage Road, 70th Street, 70th Place, 71st Street, and 72nd Street.

PCC_Key