PCC Patch 2021 Phase 1 and 2

Project Description:

Each year, the City of Urbandale patches a number of city streets that are in need of repair.  The work is divided into two projects, one in western Urbandale, and one in eastern Urbandale.  Please see below for more details of each phase.

Phase 1 West - Project Status Update - 05/04/2021

The 2021 Patch Project Phase 1 has been awarded to Shekar Engineering.  Shekar will begin saw-cutting patches in mid-May.  Residents will be notified when work will be starting in their neighborhood.

Phase 1

Phase 1 is in western Urbandale and includes the areas from 147th Street to 160th Street and from Maple Drive to Airline Avenue.  

PCC_Key

Phase 2 East - Status Update - 05/04/2021

The 2021 Patch Project Phase 2 has been awarded to Hill Contracting.  Hill Contracting will begin saw-cutting patches on Holcomb and 70th Place the first week of May.  Residents will be notified when work will be starting in their neighborhood.

Phase 2

Phase 2 is in eastern Urbandale and includes the Holcomb Avenue, the Hickman Frontage Road, 70th Street, 70th Place, 71st Street, and 72nd Street.

PCC_Key