Project Description:

This project will involve the reconstruction of 72nd Street from Douglas Avenue to just north of Prairie Avenue. This reconstruction will provide for the replacement of a 25’ wide street. The limits of this project will extend from the north side of Douglas Avenue, north along 72nd Street through the intersection with Prairie Avenue. This area does not have an adequate storm sewer system, so a new storm sewer will be added as part of the project. Storm Sewer improvements will also be added along the north side of Ridgemont Drive from 72nd Street to 74th Street.

72nd Street Reconstruction Project

Project Status Update - 09/16/2020

Stage 1 - Stage 1 is open to traffic. Work is complete.

Stage 2 – Stage 2 is open to traffic. Work is complete.

Stage 3 – Stage 3 is open to traffic. Most of the sod has been installed. The remaining sod is tentatively scheduled for next week.

Stage 4 – Stage 4 is open to traffic. Sod restoration is tentatively scheduled for next week.

Stage 5 – Stage 5 is closed to all traffic. This stage is tentatively scheduled to open by the end of the week. Sod restoration is tentatively scheduled for next week.

72nd Street is closed to all through traffic from Aurora Avenue to Douglas Avenue. It is anticipated 72nd Street will reopen at the end of the week.

As a part of the project, storm sewer services will be installed to the properties on each side of the street. Property owners are strongly encouraged to connect to the service. A grant program has been established to aid in the process. Additional information is available in the helpful downloads below.