Meredith Drive - 156th Street to 170th Street

Project Description:

This project provides for the reconstruction of Meredith Drive from 156th Street west to ¼ mile east of 170th Street as a four-lane roadway with left-turn lanes including grading, and storm sewer. The paving will be portland cement concrete with two 26-foot wide paving sections and a 28-foot grass median and a 10-foot trail on the north side. This is a joint project with the City of Clive. The project is anticipated to be completed in late spring of 2020.

Project Status Update - 5/05/2020

The contractor will be completing the remaining curb and gutter and sidewalks/ trails this spring.

The Contractor has closed the outside lanes on Meredith Drive to construct the trail and sidewalk. After all sidewalks and trails are complete, the contractor will be installing approximately 400 feet of curb and gutter. This will require the traffic control to be switched to a closure of the inside lane. The contractor will also be working on restoration.

Stage 1 is open to traffic. Temporary single lanes closures will be required for sidewalk/trail construction.

Stage 2 is open to traffic. Temporary single lanes closures will be required for sidewalk/trail construction.

Helpful Downloads