104th Reconstruction – Hickman Road to Douglas Ave

Project Description:

This project is the total reconstruction of 104th Street from Hickman Road to Douglas Parkway as a three-lane urban section roadway. This road would have one lane in each direction plus a left turn lane. Storm sewer would be installed with this project to allow the ditches to be filled and curb and gutter used on the new street. Sidewalks will be provided on both sides of 104th Street.

Project Status Update, 05/15/2019:

104th Street is closed in Stage 1 (see Road Closure Map and Staging Map below) as of Monday, April 1st.  104th Street is closed to all traffic at the creek crossing.

Utility relocation is nearly complete in Stage 1.  The Contractor, CTI, has started Stage 1 work, including culvert and storm sewer construction, water main relocations, and pavement reconstruction.  Weather permitting, Stage 1 will be complete in mid-June, at which time work will move south to Stage 2.

Please check back to this page for updates on impending closures.

Access and Work Zones:

Portions of 104th Street will be completely closed to through traffic during construction.  Access will be provided for businesses along the road during road closures.  Please follow posted signs and detours for routing around construction.

Check back here for updates on closures as work progresses.