104th Reconstruction – Hickman Road to Douglas Ave

Project Description:

This project is the total reconstruction of 104th Street from Hickman Road to Douglas Parkway as a three-lane urban section roadway. This road would have one lane in each direction plus a left turn lane. Storm sewer would be installed with this project to allow the ditches to be filled and curb and gutter used on the new street. Sidewalks will be provided on both sides of 104th Street.

Project Status Update, 03/26/2019:

104th Street will close in Stage 1 (see Staging Map below) on Monday, April 1st, weather permitting.  104th Street will be closed to all traffic at the creek crossing  The Contractor, CTI, has staked the construction limits and removed trees and shrubs in the project limts.  Utility relocation plans are currently underway.  Stage 1 includes culvert and storm sewer construction and pavement reconstruction.

Please check back to this page for notices of impending closures.

Access and Work Zones:

Portions of 104th Street will be completely closed to through traffic during construction.  Access will be provided for businesses along the road during road closures.  Please follow posted signs and detours for routing around construction.

Check back here for updates on closures as work progresses.